Home | About us | Complaint Registration | Search | Press Releases | Consumer Guide Login
BEFORE THE UTTAR PRADESH ELECTRICITY REGULATORY COMMISSION LUCKNOW
Petition No.619/09
IN THE MATTER OF:
Procurement of 500 MW Base Load Power by Madhyanchal Vidyut Vitran Nigam Ltd. under Case-1 bidding procedure issued by the Central Government under ‘Guidelines for Determination of Tariff by Bidding Process for Procurement of Power by Distribution Licensees’.
AND
IN THE MATTER OF:
UP Power Corporation Ltd. 3rd Floor, Shakti Bhawan Extn, 14,Ashok Marg, Lucknow.
  :Petitioner
AND
  Petition No.620/09
IN THE MATTER OF:
Procurement of 500 MW Base Load Power by Purvanchal Vitran Nigam Ltd. under Case-1 bidding procedure issued by the Central Government under ‘Guidelines for Determination of Tariff by Bidding Process for Procurement of Power by Distribution Licensees’.
AND
IN THE MATTER OF:
UP Power Corporation Ltd. 3rd Floor, Shakti Bhawan Extn, 14, Ashok Marg,
Lucknow.
  :Petitioner
The following were present:
1. Sri. S.K Agarwal, Director (Finance), UPPCL
2. Sri.V.K Verma, CE(Planning), UPPCL
3. Sri. Deepak Raizada, Sr.AE(Planning), UPPCL
4. Sri. Ashok Kumar, ED (T), UPPTCL
5. Sri. V.P Trivedi, CE(PS)
6. Sri. S.P Gupta, UPPCL
7. Sri. B.P Pant, EE(Power System)
8. Sri. Anuj Vashisth, PwC,
9. Sri. Shubhranshu Pathak, ED, PwC
 
ORDER
(Date of Hearing 29.7.09)
The above mentioned petitions have been filed by the petitioner in the capacity of authorized representative of Madhyanchal Vidyut Vitran Nigam Limited (MVVNL) and Purvananchal Vidyut Vitran Nigam Limited (PuVVNL) for procurement of 500 MW Base Load Power each by MVVNL and PuVVNL under Case-1 bidding procedure issued by the Central Government under ‘Guidelines for Determination of Tariff by Bidding Process for Procurement of Power by Distribution Licensees’. These petitions are similar in nature and involve common issues as such are being dealt by this single order.
The petitioner intends to establish a single stage competitive bidding process for procurement of 500 MW by delivery date, not being later than 1.4.2011. Approval of the Commission has been sought in respect to deviation from standard RFP clauses 1.3.1.
The Commission issued a public notice dt.14.7.09 in the newspapers for inviting comments/objections/suggestions of stakeholders and interested parties on the abovementioned petitions. None have made submissions in response to the above notice.
Sri. S.K Agarwal, Director (Finance) submitted, on behalf of the Petitioner, that process of procurement of power was being established to meet immediate requirement of power of MVVNL and PuVVNL in view of shortage experienced by them. Since the delivery of power was to commence not later than 1.4.2011, deviation sought in the petition had become imminent and logical. He informed that ‘RFP’ and ‘RFP documents’ have been prepared which might be issued for inviting bids if deviation was approved by the Commission. In view of the deviations sought from provisions of clause 1.3.1 of standard RFP, the Commission enquired if the petitioner intended to procure power from existing generating station(s) or from those that are to be commissioned by 31.3.2011. Sri. Agarwal replied in affirmative and stated that in light of the said delivery date, supply was possible only from existing generating stations or from those that are to be commissioned before the said delivery date and as a consequence of which, four year period specified in clause 1.3.1 of standard RFP might be relaxed as proposed in the petition.
In light of the arguments forwarded in support of the deviation, the Commission is of the considered opinion that the deviation, if allowed, should not pose any difficulty in the bid process. Therefore, the deviation is allowed, however the Petitioner shall hold a pre bid meeting within seven working days from the date of issue of ‘RFP and RFP documents’ for inviting bids. The Petitioner is further directed to approach the Commission if any deviation, other than that allowed in this petition, is made from standard RFP and standard RFP documents. The Petitioner shall keep the Commission informed of each stage of the bid process specified under clause 2.8.2 of RFP.
The petitions are disposed of.
(Rajesh Awasthi)
Chairman
Lucknow; Dated: 30th July, 2009
 
More ...
More ...
About us | Complaint Registration | Search Complaint | New Redressal System | Photo Galary | Electricity Ombudsman
Extract of Act | Useful Links | Site Map | Contact us | Feedback | Disclaimer

 

Corrosponding Office : Mr. Bejon Misra, D - 14, First Floor, Greater Kailash Enclave - II, New Delhi 110048, Phone : +91-11-40537140
EMail : bejonmisra@hotmail.com, bejonmisra@bijlidost.org
Best Viewed in 800 * 600 Resolution Designed Developed and maintained By Comtech Solutions